Tropical Storm Isaias Recovery Efforts

Shawyn Patterson-Howard
2 min readAug 7, 2020

--

DPW began with 87 Issues on Tuesday evening

CON-EDISON: 2,945 Customers Still Without Power

Pushed Con Edison for Additional Line Crews to be dispatched from other states to complete Transformer Repairs and Primary Lines Restoration

PHASE 1 — Roads Blocked

We now have:

3 Blocked roads remaining to be cleared tomorrow

  • Prospect Ave
  • Hutchinson Blvd
  • Washington St

PHASE 2 — Trees on Homes
12 Trees on homes will begin being removed starting tomorrow

PHASE 3 — City-Wide Debris Cleanup will take place throughout the day.

Mount Vernon will be having a food distribution today at 3pm at the Doles Center.

For those looking for reimbursement for spoiled items, you can file a claim with Con Edison at https://www.coned.com/en/services-and-outages/claim-form

--

--